The Kindergarten in Mak-Jolly School constitutes of 121 children in the building from 2012 and the building is now too old and too small.
The building is made out of rids and papyrus mats which we always replace every 3 months because of the termites. We have occasionally sprayed but despite all that the building has now become weak and requires a new one.
Dear Parents, Family and friends of Mak-Jolly School we need to raise 110.000,- Danish kroner (58 million Uganda shillings) to have
a good building with bricks and a good roof, same as our primary school building. (See budget further down this page)
Unfortunately, we only have one year to raise the money. We cannot do this alone; we are therefore calling upon all our friends, sponsors, parents and relatives to help with what you can. No amount is too little and ideas of how to raise the money are welcome.
This kindergarten is the rock of this school. It opened in 2012 with only 8 children in kindergarten and it has grown into a school up to primary 6 with
a total of 284 pupils. We want to thank all those who helped us construct the primary school building and we are calling upon your help once again.
We are always grateful towards all those who have made it possible for us to provide a good education for the children in Kiryandongo, Uganda.
We would not be able to take care of 284 children without your help.
BE PART OF THE FUNDRAISE
HELP US CONSTRUCT A NEW KINDERGARTEN BUILDING
Buy a brick and have your name inscribed on the Mak-Jolly Wall of Fame. See which bricks are available here!
NB: We have started the construction of the Kindergarten building January 2018. See photo in Gallery. Help us finish it, Please donate.
You can donate through:
Mobile Money Uganda: +256 782720955 (Maureen Kabasinguzi, Uganda), or +256 786694212 (at Mak-Jolly school, Uganda)
Mobile Pay Denmark: +45 94743
Money transfer: Bank Reg.no. 1569 Ac.no. 0001436244
Please mark the donation: "Building" and please write an e-mail regarding your brick number or anonymity.
Contact Info:
E-mail: contact@makjolly.com
We thank all contributors may God bless you!
Budget for a new kindergarten building:
Step 1 | ||||
Foundation: | ||||
trips, pieces, kilo, bags | Uganda schillings | Uganda schillings | Danish kroner | |
Red stones | 17 | 60000 | 1020000 | |
Sand | 10 | 50000 | 500000 | |
Bricks | 10 | 200000 | 2000000 | |
Cement | 70 | 35000 | 2450000 | |
Water | 200000 | |||
Transport | 330000 | |||
Labour | 3000000 | |||
Total step 1 | 9.500.000 ugs | 18.050 kr. | ||
Step 2 | ||||
Wall to beam: | ||||
trips, pieces, kilo, bags | Uganda schillings | Uganda schillings | Danish kroner | |
Sand | 8 | 50000 | 400000 | |
Cement | 60 | 35000 | 2100000 | |
Bricks | 20 | 200000 | 4000000 | |
Iron bars 10ml | 33 | 22000 | 726000 | |
Iron bars 12ml | 33 | 24000 | 792000 | |
Cirup | 80 | 3000 | 240000 | |
Nails 5 inch | 8 | 6000 | 48000 | |
Nails 4 inch | 7 | 6000 | 42000 | |
Nails 3 inch | 7 | 6000 | 42000 | |
Nails 2,5 inch | 5 | 5000 | 25000 | |
White stones | 2 | 220000 | 440000 | |
Water | 200000 | |||
Transport | 445000 | |||
Labour | 3000000 | |||
Total for step 2 | 12.500.000 ugs | 23.750 kr. | ||
Step 3 | ||||
Roofing: | ||||
trips, pieces, kilo, bags | Uganda schillings | Uganda schillings | Danish Kroner | |
Timber 2by6 | 36 | 8000 | 288000 | |
Timber 2by4 | 130 | 8000 | 1040000 | |
Timber 2by3 | 90 | 7000 | 630000 | |
Timber 3by4 | 30 | 10000 | 300000 | |
Nails 6 inch | 25 | 6000 | 150000 | |
Nails 5 inch | 30 | 6000 | 180000 | |
Nails 4 inch | 30 | 6000 | 180000 | |
Nails 3 inch | 15 | 6000 | 90000 | |
Nails 2,5 inch | 6 | 5000 | 30000 | |
Cirup | 30 | 3000 | 90000 | |
Iron sheets & ridges | 96 | 90000 | 8640000 | |
Roofing nails | 40 | 7000 | 280000 | |
Rubber | 25 | 4000 | 100000 | |
Transport | 1002000 | |||
Labour | 3000000 | |||
Total for step 3 | 16.000.000 ugs | 30.400 kr. | ||
Step 4 | ||||
trips, pieces, kilo, bags | Uganda schillings | Uganda schillings | Danish kroner | |
Rough floor: | ||||
White stones | 15 | 220000 | 3300000 | |
Sand | 38 | 50000 | 1900000 | |
Cement | 38 | 35000 | 1330000 | |
Smooth floor: | ||||
Cement | 32 | 35000 | 1120000 | |
Sand | 2 | 50000 | 100000 | |
Plastering: | ||||
Cement | 39 | 35000 | 1365000 | |
Sand | 20 | 50000 | 1000000 | |
Painting | 3500000 | |||
Windows | 14 | 150000 | 2100000 | |
Doors | 6 | 300000 | 1800000 | |
Water | 300000 | |||
Transport | 185000 | |||
Labaour | 2000000 | |||
Total for step 4 | 20.000.000 ugs | 38.000 kr. | ||
Total for all steps | 58.000.000 ugs | 110.200 kr. | ||
(Kurs 0,0019) | ||||