Fundraise for a new kindergarten building

Fundraise for a new kindergarten

The Kindergarten in Mak-Jolly School constitutes of 121 children in the building from 2012 and the building is now too old and too small.


The building is made out of rids and papyrus mats which we always replace every 3 months because of the termites. We have occasionally sprayed but despite all that the building has now become weak and requires a new one.


Dear Parents, Family and friends of Mak-Jolly School we need to raise 110.000,- Danish kroner  (58 million Uganda shillings) to have

a good building with bricks and a good roof, same as our primary school building. (See budget further down this page)

















Unfortunately, we only have one year to raise the money. We cannot do this alone; we are therefore calling upon all our friends, sponsors, parents and relatives to help with what you can. No amount is too little and ideas of how to raise the money are welcome.


This kindergarten is the rock of this school. It opened in 2012 with only 8 children in kindergarten and it has grown into a school up to primary 6 with

a total of 284 pupils. We want to thank all those who helped us construct the primary school building and we are calling upon your help once again.


We are always grateful towards all those who have made it possible for us to provide a good education for the children in Kiryandongo, Uganda.


We would not be able to take care of 284 children without your help.


BE PART OF THE FUNDRAISE

HELP US CONSTRUCT A NEW KINDERGARTEN BUILDING


Buy a brick and have your name inscribed on the Mak-Jolly Wall of Fame. See which bricks are available here!


NB: We have started the construction of the Kindergarten building January 2018. See photo in Gallery. Help us finish it, Please donate.



You can donate through:



Mobile Money Uganda: +256 782720955  (Maureen Kabasinguzi, Uganda), or  +256 786694212  (at Mak-Jolly school, Uganda)


Mobile Pay Denmark: +45 94743


Money transfer: Bank  Reg.no. 1569    Ac.no. 0001436244


Please mark the donation: "Building" and please write an e-mail regarding your brick number or anonymity.


Contact Info:


E-mail: contact@makjolly.com



We thank all contributors may God bless you!


Budget for a new kindergarten building:


Step 1






Foundation:






trips, pieces, kilo, bags

Uganda schillings

Uganda schillings

Danish kroner






Red stones

17

60000

1020000


Sand

10

50000

500000


Bricks

10

200000

2000000


Cement

70

35000

2450000


Water



200000


Transport



330000


Labour



3000000







Total step 1



9.500.000 ugs

18.050 kr.






Step 2










Wall to beam:






trips, pieces, kilo, bags

Uganda schillings

Uganda schillings

Danish kroner






Sand

8

50000

400000


Cement

60

35000

2100000


Bricks

20

200000

4000000


Iron bars 10ml

33

22000

726000


Iron bars 12ml

33

24000

792000


Cirup

80

3000

240000


Nails 5 inch

8

6000

48000


Nails 4 inch

7

6000

42000


Nails 3 inch

7

6000

42000


Nails 2,5 inch

5

5000

25000


White stones

2

220000

440000


Water



200000


Transport



445000


Labour



3000000







Total for step 2



12.500.000 ugs

23.750 kr.






Step 3










Roofing:






trips, pieces, kilo, bags

Uganda schillings

Uganda schillings

Danish Kroner






Timber 2by6

36

8000

288000


Timber 2by4

130

8000

1040000


Timber 2by3

90

7000

630000


Timber 3by4

30

10000

300000


Nails 6 inch

25

6000

150000


Nails 5 inch

30

6000

180000


Nails 4 inch

30

6000

180000


Nails 3 inch

15

6000

90000


Nails 2,5 inch

6

5000

30000


Cirup

30

3000

90000


Iron sheets & ridges

96

90000

8640000


Roofing nails

40

7000

280000


Rubber

25

4000

100000


Transport



1002000


Labour



3000000







Total for step 3



16.000.000 ugs

30.400 kr.






Step 4






trips, pieces, kilo, bags

Uganda schillings

Uganda schillings

Danish kroner

Rough floor:





White stones

15

220000

3300000


Sand

38

50000

1900000


Cement

38

35000

1330000


Smooth floor:





Cement

32

35000

1120000


Sand

2

50000

100000


Plastering:





Cement

39

35000

1365000


Sand

20

50000

1000000


Painting



3500000


Windows

14

150000

2100000


Doors

6

300000

1800000


Water



300000


Transport



185000


Labaour



2000000







Total for step 4



20.000.000 ugs

38.000 kr.






Total for all steps



58.000.000 ugs

110.200 kr.

(Kurs 0,0019)